Effective timeline management ensures shopfitting projects meet deadlines while maintaining quality standards.
Pre-construction Phase (15-25% of timeline):
Design finalization (3-7 days)
Material procurement (7-14 days lead time)
Permits/approvals (varies by municipality)
Construction Phase (60-70%):
Core build-out (2-4 weeks for 1000sqft retail)
Fixture installation (1-2 weeks)
Services integration (electrical/plumbing 3-5 days)
Snagging Phase (10-15%):
Punch list resolution (48hr standard)
Client walkthroughs (2-3 iterations)
Gantt charts with 5-10% float time
Critical path method (CPM) analysis
4D BIM simulations for complex projects
Industry Benchmarks:
6-8 weeks for standard retail unit (1500sqft)
2-day buffer per £50k project value
Stakeholder management requires structured communication protocols.
Trade Sequencing:
Demolition (if required)
First fix (electrical/mechanical rough-ins)
Drywall/flooring
Second fix (finish carpentry/lighting)
Performance Metrics:
95% on-time delivery expectation
3-strike policy for quality violations
Communication Protocol:
Weekly progress reports (standardized templates)
24hr response time SLA
Change Order Process:
Written authorization required
15% minimum markup on alterations
48hr review period
Documentation Requirements:
Daily site diaries (photos + notes)
RFI log (response within 24 working hours)
Optimized site setup directly impacts productivity and safety.
Zoning Requirements:
Material storage (dedicated 20% of floor area)
Work zones (500mm clearance around all sides)
Client access pathways (minimum 900mm width)
Logistics Management:
Just-in-time delivery scheduling
Waste segregation stations (3-bin system)
Mandatory Controls:
Perimeter screening (2.4m height minimum)
Dust containment (0.5mg/m³ threshold)
Noise curfews (07:00-18:00 standard)
Tool Management:
PAT testing every 3 months
Lockout-tagout procedures
Proactive issue resolution maintains project momentum.
Assess impact (cost/time/quality)
Identify 3 solution options
Client consultation (>£5k variations)
Implement with documentation
Contingency Planning:
10% budget reserve
5% schedule float
Preferred subcontractor list
Systematic completion procedures ensure client satisfaction.
Three-Stage Inspection:
Trade-specific snagging
PM quality audit
Client walkthrough
Acceptance Criteria:
0 critical defects (safety/functionality)
≤3 minor defects per 100sqm
As-built Drawings (CAD + PDF formats)
O&M Manuals (minimum 50-page dossier)
Warranty Packages (component-specific)
Training Records (staff sign-off sheets)
30-day defects liability period
2hr minimum systems training
Emergency contact protocol
Performance Metrics:
98% defect-free handover target
72hr snag resolution guarantee
This module provides the structural framework for delivering shopfitting projects on time, within budget, and to exacting quality standards. The methodologies outlined combine construction best practices with retail-specific requirements, ensuring operational readiness from first fix to grand opening.