Objective: Construct a suspended slab (elevated concrete slab) to simulate real-world high-rise or bridge applications.
Step-by-Step Execution:
Design Review:
Study shop drawings for beam/slab dimensions, prop spacing, and reinforcement clearances.
Erecting Supports:
Install adjustable steel props (e.g., Acrow props) at 1.2m intervals.
Ensure base plates are on solid ground or shoring boards.
Flying Form Installation:
Assemble modular deck panels (plywood + H20 beams) and secure with dropheads.
Edge Formwork:
Fix timber/steel shutters for slab thickness control (e.g., 200mm).
Bracing & Alignment:
Diagonal braces to prevent lateral movement during pouring.
Key Checks:
Confirm prop load capacity matches design (e.g., 20 kN/prop).
Verify no gaps at formwork joints to prevent leaks.
Objective: Achieve ±3mm accuracy in formwork positioning.
Procedure:
Set up a rotating laser level (e.g., Leica Rugby) at a stable benchmark.
Mark elevation points on vertical formwork (e.g., column molds).
Adjust formwork until all marks align with the laser plane.
Common Errors & Fixes:
Error: Laser misalignment due to vibration.
Fix: Use a remote trigger to minimize disturbance.
Objective: Safely strip formwork while maximizing reuse cycles.
Safe Stripping Sequence:
**Wait for concrete to reach minimum strength (e.g., 15 MPa for slab props).
Remove side forms first, then lower props gradually.
Avoid prying—use timber wedges to prevent edge damage.
Reuse Optimization:
Plywood Care:
Clean with plastic scrapers (no metal tools).
Apply form oil before reuse.
Steel/Aluminum Forms:
Inspect for dents or bent edges; repair before reuse.
Sustainability Focus:
Recycle damaged plywood into filler pieces.
Track reuse cycles to retire forms after max lifespan (e.g., 300 cycles for aluminum).
Scenario: Simulate a prop collapse during stripping.
Response:
Emergency shutdown, evacuate area.
Reinforce with additional shoring before resuming.
Suspended slabs require multi-level bracing and load-rated props.
Laser levels eliminate guesswork in alignment.
Gentle demolition extends formwork lifespan.